IndustriesManufacturing

Manufacturing energy: the charges behind the unit rate.

On a half-hourly supply the unit rate is only part of the bill. Capacity, network charges and levies sit behind it, and several of them carry reliefs a manufacturer may be entitled to. We start with your half-hourly data, check each charge, then buy the power on the right contract.

For factories, engineering works, food and drink production, and processing sites.

What we find

Where a factory loses the money.

The four things we check on a manufacturing site before we price anything.

1

Agreed capacity set years ago

You pay a daily charge for every kVA held for the site, used or not. If your real peak sits well under the agreed figure, you're paying for headroom. Go over it and there's an excess charge instead.

2

The levy at the full rate

A site in a Climate Change Agreement gets 92% off the levy on electricity and 89% off on gas. Without an agreement, or with the supplier certificate missing, it's charged in full.

3

Trade effluent on discharge you don't make

Water that goes into product, cooling or steam never reaches the drain. The effluent bill should reflect what's really discharged, and a non-return allowance takes the rest off the sewerage charge.

4

Meter contracts that renew themselves

On half-hourly sites the meter operator and data contracts are separate from the supply, and they quietly auto-renew. They're worth a look at every renewal.

The rules

Four reliefs worth checking.

01

Climate Change Agreements

A voluntary agreement to meet efficiency targets, in exchange for 92% off the levy on electricity and 89% off on gas.

02

Mineralogical and metallurgical processes

Energy used in these processes is exempt from the main rates of the levy altogether. The relief is claimed through the supplier.

03

The British Industrial Competitiveness Scheme

From April 2027 eligible manufacturers stop paying the Renewables Obligation and Feed-in Tariff costs in their electricity, with Capacity Market costs following in October 2027. The government puts it at up to a quarter off the bill. Eligibility goes by industry and product codes, site by site.

04

The Supercharger

Around 500 of the most energy-intensive firms have had 90% off electricity network charges since April 2026, up from 60%.

Applications for the scheme's first year close at 11:59pm on 30 November 2026.

Agreed capacity

Paying for headroom you don't use.

Your agreed capacity is on the bill, in kVA. So is the daily charge for it. Your half-hourly data shows the most you really drew.

Put the three in and see what the gap costs. Keep a margin when you reduce it: go over the agreed figure and the excess is charged, and capacity you give up may not be there if the site grows.

From your bill Example figures
10%
Headroom you pay for and don't use
£2,902a year

159 kVA of the 500 kVA you pay for sits above your peak and the margin. At 5p per kVA per day, that is £2,902 a year.

Your agreed capacity500 kVA, £9,125 a year
Highest demand Margin kept Unused headroom
Part of the agreed capacityCapacityCost a year
Highest demand310 kVA£5,658
Margin kept31 kVA£566
Unused headroom159 kVA£2,902
Agreed capacity500 kVA£9,125

Uses the three figures you enter and a 365-day year. A guide, not a quote. Any change to agreed capacity is made with the network operator.

Have the real data checked
What we handle

What we take on for manufacturers.

Half-hourly electricity

Fixed or bought in tranches across the term, with the non-commodity charges set out so you can see what moves.

Business electricity →

Gas

Process and heating gas priced across the panel, with the annual quantity checked against real consumption.

Business gas →

Water & trade effluent

Consents, Mogden-formula charges, and whether you're paying for discharge you don't actually make.

Business water →

Waste

Production waste, recycling and one-off clearances on one contract, with the transfer notes kept in order.

Business waste →

Metering

Half-hourly data in a form you can use, and meter operator contracts checked at every renewal.

Metering →
How it works

Three steps. You do the first.

Send us a bill

One recent invoice, and your authority for us to request the half-hourly data.

We read the data, then go to market

Capacity, levy and metering checked first. Then the full panel, fixed and flexible, side by side.

You choose, we switch

Paperwork, supplier chasing and the renewal diary. Nothing changes at the meter.

Manufacturing FAQ

Straight answers.

The maximum demand, in kVA, that the network operator holds available for your site. You pay a daily charge for each kVA whether you use it or not, and an excess charge if you go over.

Other sectors Charities Hospitality & pubs Retail Care homes Property Business support services Education Agriculture Hotels & holiday parks Healthcare, dental & vets Leisure & sports clubs All industries
Start here

Send us one bill.

A photo of a recent bill for each supply is enough to start. A named account manager rings you back within one working day.

The rules on this page were checked on 25 November 2026 against the published Climate Change Levy rates, GOV.UK guidance on exemptions from the Climate Change Levy, the government's announcement of the British Industrial Competitiveness Scheme, the scheme's guidance for applicants and the water industry's customer guidance on return to sewer allowances. It's general guidance, not tax or legal advice.